[China paint information] (I) overview of the proposed project
Project Name: Chongqing Three Gorges paint Co., Ltd. "annual output of 50000 tons of environmental protection and energy saving water-based coating project"
construction nature: new
construction location: pharmaceutical and chemical area of Degan Industrial Park Chongqing Three Gorges paint Co., Ltd. existing plant area
electronic universal tension machine measurement system construction investment: 180 million yuan
production scale: the total production scale is 50000t/a water-based coatings, including 20000T/a water-based industrial coatings and 30000t/a water-based building coatings
product scheme: 10000t/a anticorrosive coating; Other industrial coatings 10000t/a; Heat reflective thermal insulation paint 5000t/a; High stain resistance exterior wall paint 10000t/a; Interior wall coating 15000t/a
land scale: the project covers an area of 20651.58m2, with a green space rate of 19%
production system: in the production workshop, except for the grinding position, which implements four shifts and three shifts, other positions implement the two shift system; The management department implements the day shift system. Annual working days: 250 days
labor quota: 184 people in total
construction period and implementation progress: from February 2009 to February 2011, the construction period is 2 years
(II) overview of the possible impact of the construction project on the environment
(1) waste gas: dust is generated in the process of raw material weighing, feeding, mixing and mixing, which may have an adverse impact on the ambient air
(2) wastewater: equipment, ground and filter washing wastewater; Demineralized water station wastewater; Laboratory wastewater and domestic sewage may have adverse effects on the surface environment
(3) noise: the main noise sources are air compressors, high-speed dispersers, Sanders, material pumps, cooling towers, fans, etc., which may have a certain impact on the surrounding environment
(4) solid waste: the process waste residue discharged by the water-based coating device mainly includes all kinds of waste raw material packaging bags (barrels), mechanical impurities and filter residue generated by filtration. It is a general industrial solid waste, which may have a certain impact on the surrounding environment
(III) key points of countermeasures and measures to prevent or mitigate adverse environmental impacts
(1) waste gas: for the dust generated in the process of raw material weighing, feeding, mixing and mixing, 298 molded polystyrene foam for thermal insulation project plans to set up dust hoods at the dust production points in the mixing process, send the dust to the dust collector for treatment after dust collection, and set up a set of dust removal system in the industrial coating and architectural coating workshops, After treatment, it is discharged through a 15m high exhaust funnel. The emission concentration of dust after treatment meets the requirements of class II standard of integrated emission standard of air pollutants (GB). After taking environmental protection prevention and control measures, it has little impact on the ambient air quality
(2) waste water: the waste water of the proposed project mainly contains organic pollutants and various pigments and fillers, which are biochemical. The waste water is discharged into the sewage treatment plant of degan industrial park after being pretreated by the sewage treatment station in the plant area to reach the level III standard. After the level II biochemical treatment reaches the level I standard of the comprehensive sewage discharge standard, it is discharged into the Yangtze River. It has no obvious impact on the water quality in the lower reaches of the Yangtze River outfall
(3) noise: the noise sources of the project mainly include air compressors, fans, material pumps, high-speed dispersers, sand mills, cooling towers, etc., and the noise level is generally between 70~100db (a). In the design and model selection, low-noise equipment shall be selected as far as possible, and sound insulation, noise elimination and vibration reduction measures shall be taken respectively. After the measures are taken, the noise can be controlled below 85dB, which meets the noise health standard of industrial enterprises. It meets the requirements of class 3 standards in the standard for noise at boundary of industrial enterprises (GB). There is no obvious impact on the external environment after the measures
(4) solid waste: properly dispose of it and send it to Jiangjin District landfill disposal site in the near future; In the long term, it will be sent to the general industrial solid waste disposal center in the main city of Chongqing. In strict accordance with the requirements of cleaner production and circular economy, the "three wastes" emission of enterprises is minimized, and the requirements of total amount control and emission standards are met. After the measures, there is no obvious impact on the external environment
the above waste gas, waste water and noise treatment measures have mature technology, good treatment effect, and are economical and reasonable. Solid waste can be effectively disposed of. The pollution measures of the proposed project are reasonable and feasible
(IV) key points of the conclusion of environmental impact assessment put forward in the environmental impact report
Chongqing Three Gorges paint Co., Ltd. "50000 tons of environmental protection and energy-saving water-based coating project" is constructed in line with the national industrial policy and the requirements of the "Eleventh Five Year plan" development plan of Chongqing chemical industry; It conforms to the overall development plan of Jiangjin district and the industrial positioning and development plan of Degan Industrial Park. The project adopts advanced and energy-saving production technology and mature and reliable environmental protection technical measures, with obvious characteristics of cleaner production. On the basis of meeting the requirements of regional environmental functions, as long as the construction unit implements the environmental protection treatment measures proposed in the report, the pollutants can be discharged up to the standard, and the total amount of pollutants can be controlled. There will be no obvious impact on the environment. Therefore, from the perspective of environmental protection, it is feasible for the proposed project to be constructed at the proposed site
(V) ways and periods for the public to consult the simplified environmental impact report
the public can consult the simplified environmental impact report at the Chongqing Academy of Environmental Sciences or Chongqing Three Gorges paint Co., Ltd., the environmental assessment unit of the project, within 10 days after the announcement
(VI) scope and precautions of soliciting public opinions
(1) scope of soliciting public opinions
is located within the evaluation scope and may be directly affected by the project construction and the public in Degan Industrial Park and degan area
(2) precautions
the public should objectively and truly reflect their opinions on environmental protection of project construction, and sign when submitting written opinions
(VII) specific forms of soliciting public opinions
questionnaire survey is used to solicit public opinions, supplemented by letters, faxes, emails and other forms
(VIII) starting and ending time of public comments
the public can submit written comments to the construction unit or environmental impact assessment unit by letter, fax, email or other convenient means within 10 days after the publication of this announcement. At present, the domestic peek market has not been fully opened, and it will not be accepted after the expiration of the time limit
(IX) Contact information
project construction unit: Chongqing Three Gorges paint Co., Ltd.
address: Degan Industrial Park, Chongqing zip code: 402284
contact person: Mr. Hu
: Fax:
project environmental impact assessment unit: huanchongqing Academy of Environmental Sciences
address: No. 252, Ranjiaba Qishan Road, dashiba, Jiangbei District, Chongqing zip code: 400021
then start the experiment
contact person: Mr. Li
Fax:
email:cqeia501@